Building new section to production clinker (1999')

sight of old kiln section
sight of old kiln section - planetary cooler
new kiln - foundations supports works
new kiln - sight of foundation frame
new kiln elements - before assembly
supportive construction to kiln assembly - firm A.L.E.
supportive construction to kiln assembly - firm A.L.E.
assembly of kiln section - BALDWINS crane works
assembly of kiln section - BALDWINS crane works
support section - sight before frame foundation
sight of old kiln section
sight of old kiln section
sight of Preheater tower
ZMP had the pleasure of realizing fully engineering service assembly new section of clinker furnace. The works were running at commission Mostostal Będzin S.A. The coordinator those works was F.L. SMITDH & CO A/S represented by Peter Sondergaard. Ours involve in range of works measurement, consultancy and analytical analysis received a high recognition from coordinator and client this object. So, credentials placed below are proof ours credibility.